We will build a research center in Lublin

On Friday, July 9, 2021, we signed a contract for the construction of the Research Center building. The investment will be set up in Lublin, at the request of Biomed Lublin, a factory for the production of serums and vaccines s. a.
Under the contract, the building of the research center will be built. It will have a drug production line. The project is part of the Center for Biotechnological Innovations-onco BCG plant, which will improve technologies related to vaccinology in the prevention of tuberculosis (BCG) and immunology in the treatment of cancer.
Investments in numbers:
- Number of buildings: 1
- Number of floors: 2
- Built-up area: 1374 m2
- Usable area: 2,422. 1 m2
- Total area: 2764.4 m2
- Building height: 11.9 m
- Contract value: PLN 32,999 million net
- Work will begin in July 2021.
- The construction completion date is scheduled for September 2022.